POWER-TO-X BY KASSØ

Adding Engineering is the main consultant in the design of a methanol plant for European Energy. The plant is the first full-scale plant for the production of green methanol and is being built near Aabenraa. Adding Engineering helps European Energy from start to finish and with many technical disciplines.

Adding Engineering has been involved in the project from the very beginning.

At the Kassø plant, we contribute with engineering on the methanol synthesis plant in close cooperation with the customer. Adding has, among other things, executed P&I diagrams, general arrangement drawings, GA and detail arrangements, including steel and pipe constructions incl. calculations of flex and stress. In addition, technical specifications for the tender and purchase of main components such as hydrogen and CO2 compressors, CO2 systems, dry & subcoolers, pumps, valves etc. as well as laying out the cooling water system, N2 system and instrument air.

 

The tasks included, among other things:

P&I charts

 

  • Drawing and evaluation of P&I diagrams including process diagrams

 

General Arrangement, GA and design of pipes and steel:

 

  • General Arrangements drawn in AutoCad 3D Plant

  • Steel constructions for main installations and pipe bridges, etc.

  • Pipe design incl. strength calculations on main and sub-plants

  • Workshop documentation, pipe isometrics, support lists, pipe lists, valve list

 

Calculations and layout:

  • Layout of pipe sizes and component services

  • Flex and stress - calculations in ROHR 2 of approx. 600 tubes

  • Dimensioning of the cooling water system

  • Circulation number calculations on distillation column

  • Calculation and dimensioning of insulation

  • Foundation loads and drawings

 

Coordination and structuring:

 

  • Handling of approvals by 3rd parties

  • Document flow

  • Production follow-up

 

Technical specifications for the purchase of, among other things:

 

  • Hydrogen and CO2 compressor plant

  • Heat pump for district heating production approx. 7 MW

  • Valves for hydrogen, CO2 and other media

  • Pipes, steel, heat exchangers, pumps, dry coolers, chillers etc.

"Adding Engineering works with complex technical tasks and projects for us. We have chosen Adding Engineering because of their high professional level. Adding Engineering is flexible and provides a professional service, and we feel valued as a customer."

 

Anders Brendstrup, Head of EPS – Power to X, European Energy

EE_Square_DarkGreen_CMYK.png

Power-to-X and green transition at Adding Engineering

 

We contribute to the green transition with engineering and project management in several areas such as:

+ Methanol plant

+ Hydrogen production

+ Wind turbine industry

+ Gasification of plastic to produce new plastic

+ Electric boilers

+ Heat pumps

+ Fuel cells

+ Combined cycle plant

KONTAKT OS PÅ 70 23 45 55, ELLER UDFYLD FORMULAREN NEDENFOR,
HVIS VI SKAL HJÆLPE DIG MED ET LIGNENDE PROJEKT

Tak for din besked!

bottom of page